Updates beginning Jan. 27-28:
Men's Locker Room: CLOSED and moved to the all-gender locker room
(Beginning Jan. 27: lockers in row #1 [hallway] may be checked out)
Women's Staff Dressing Room: CLOSED
(Lockers in the general women's locker room may be checked out at any time)
All-Gender Locker Room: will be temporarily moved to the all-gender restroom/shower room on the field house mezzanine.
Basement and basement offices: CLOSED
Multipurpose Room: CLOSED
Phase 1A
Construction - these areas will be closed and relocated January 2025 to May 2025
- Current Men's locker room will be closed and signs posted for the new location
- All-Gender locker room will be relocated to the field house mezzanine adjacent to the gym - signs will be posted
- Women's Staff locker room will be closed and the general locker room will be the alternate location
- Basement offices and Erg room will be closed and under construction
- Kendall Multipurpose Room will be closed and the Field House Lounge is the alternate location
Phase 1B
End of February 2025 to June 2025
- Gymnasium will be closed and unavailable
Phase 2
June 2025 to January 2026
- Varsity and General women's locker room is closed
- All-Gender Locker room is located on the mezzanine level of the field house and signs will be posted
- New staff men's and women's locker rooms will be open for general/community use
- Field House Lounge is closed
August 2025
- Basement suite of locker rooms open
- Multipurpose Room open and available
- Erg room open